Doncarb Graphite completes overhaul of its press

Chelyabinsk, December 24, 2019. Doncarb Graphite's Chelyabinsk site has completed the overhaul of the press it uses to produce blanks for structural graphites, the company's main product.

The horizontal broaching hydraulic press produces blanks of different diameters (80 through 500 mm) and cross-section sizes. The blanks are then baked and graphitized, to further produce artificial graphites of different grades.

Within the overhaul project, the press's main and auxiliary equipment was repaired and replaced. The project costs totaled about RUB 3 million. The overhaul required a planned shutdown at the site and was performed in a single month in strict adherence with the approved schedule.

The Managing Director of Doncarb Graphite noted that "the overhaul of the hydraulic press is one stage in the planned upgrading of the Company's technical facilities. It is one of the most important stages, since we rely on the press's uninterrupted operation to meet all of the Company's production targets".

This year's renovations at the Chelyabinsk site of Doncarb Graphite amounted to RUB 161.5 million. The largest projects are the overhaul of two graphitization furnaces and crane equipment. The large-scale renovation of lifting devices was performed in Unit 4, while the infrastructure was repaired and replaced in all shops.

EL 6 CHELYABINSK IS IMPLEMENTING THE PLANT OFFICE RECONSTRUCTION PROJECT
CHELYABINSK SITE RUNS OHS QUIZ
THE ANODE BLOCK BAKING LINE RESUMED OPERATION AT EL 6 CHELYABINSK
Ilya Belyakov Appointed Director of EL6 Chelyabinsk
CONSOLIDATION OF ASSETS OF EL 6 (FORMERLY EPM GROUP) HAS BEEN COMPLETED
DONCARB GRAPHITE LAUNCHED A NEW PRODUCT FOR POWER GENERATION
EPM GROUP AND GOVERNMENT OF THE CHELYABINSK REGION SIGN ENVIRONMENTAL AGREEMENT
DONCARB GRAPHITE TO TAKE PART IN THE KHIMIA 2020 EXHIBITION
DONCARB GRAPHITE STARTS SELLING ISOSTATIC GRAPHITE AT A SPECIAL PRICE
Unique anodes by EPM Group for magnesium electrolyzers go to serial production
DONCARB GRAPHITE COMPLETES THE COOLING SYSTEM UPGRADE INVESTMENT PROJECT
Doncarb Graphite completes overhaul of its press
EPM-Chelyabinsk Electrode Plant shuts down anode production
Donсarb Grafit has put new equipment into operation
yana ENERGOPROM Group Put Into Operation the First Private Environmental Monitoring Station in Chelyabinsk
ENERGOPROM Group Put Into Operation the First Private Environmental Monitoring Station in Chelyabinsk
"Doncarb Graphite" completed reconstruction of the calcining furnace
yana The Chelyabinsk plants of ENERGOPROM Group present their environmental initiatives to regional experts
The Chelyabinsk plants of ENERGOPROM Group present their environmental initiatives to regional experts
Chelyabinsk Branches of ENERGOPROM Have Created an Integrated Environmental Center