News El 6 Novocherkassk

STORAGE AND SHIPPING OF FINISHED PRODUCTS WILL BE MORE CONVENIENT AT EL 6 NOVOCHERKASSK

Novocherkassk, September 22, 2023: El 6 Novocherkassk is constructing a new warehouse for finished products. After completing this project, shipping graphitized electrodes and other products will be faster and more convenient.

Consumer companies' trucks will no longer have to enter the central part of the factory to load electrodes. The new warehouse is located at the side of the factory. Fished products will be delivered to the warehouse from the Electrode Products Machining Shop (EPMS) by a new railway track.

Today, construction of the facility proceeds according to the approved schedule: the design documents have been developed; the construction permit has been obtained; soil compaction and warehouse foundation construction was completed, etc. Completion of the work is scheduled for December this year.

At the first stage, the warehouse floor area will be almost 1.5 thousand square meters.

NEW BENEFITS FOR EL 6 NOVOCHERKASSK EMPLOYEES
EL 6 NOVOCHERKASSK OPENED A NEW WAREHOUSE FOR FINISHED PRODUCTS
MEDICAL CENTER SUPPORTED BY EL 6 NOVOCHERKASSK OPENS IN NOVOCHERKASSK INDUSTRIAL DISTRICT
EL 6 NOVOCHERKASSK LAUNCHED A NEW RE-FIRING FURNACE INTO COMMERCIAL OPERATION
STORAGE AND SHIPPING OF FINISHED PRODUCTS WILL BE MORE CONVENIENT AT EL 6 NOVOCHERKASSK
EL 6 NOVOCHERKASSK: GRAPHITIZATION SHOP GETS NEW DUST & GAS SCRUBBING EQUIPMENT
DEPUTIES OF NOVOCHERKASSK CITY DUMA VISIT EL6 NOVOCHERKASSK
CONSOLIDATION OF ASSETS OF EL 6 (FORMERLY EPM GROUP) HAS BEEN COMPLETED
SERGEY ELKOV WAS APPOINTED TO THE POSITION OF THE MANAGING DIRECTOR OF EPM-NOVOCHERKASSK ELECTRODE PLANT
DEPUTY MINISTER OF TRADE AND INDUSTRY OF THE RUSSIAN FEDERATION VASILY OSMAKOV VISITS EPM-NEP
EPM-NOVOCHERKASSK ELECTRODE PLANT CONFIRMED THE COMPLIANCE OF THEIR MANAGEMENT SYSTEM WITH THE REQUIREMENTS OF INTERNATIONAL STANDARDS
EPM-NOVOCHERKASSK ELECTRODE PLANT CONFIRMED THE COMPLIANCE OF THEIR MANAGEMENT SYSTEM
EPM GROUP PUT INTO OPERATION MODERN FOUR-CHAMBER DIRECT HEATING GRAPHITE FURNACE
EPM Group completes project as part of cpecial investment contact
EPM group inaugurated the new RIEDHAMMER furnace at EPM-NEZ
Construction of a modern RIEDHAMMER furnace complete at EPM – NEP
A robot-assisted nipple manufacturing centre has been officially commisioned at EPM-NEP
Equipment Delivered to EPM-NEP Nipple Centre
EPM-NEP will have new high-precision measuring equipment for graphite electrode nipples
Novocherkassk Electrode Plant Started Preparatory Works for New RIEDHAMMER Furnace
ENERGOPROM has commissioned a new pitch impregnation line at Novocherkassk Electrode Plant
Novocherkassk Electrode Plant launches modernized baking furnace
Evgeniy Churikov Appointed Managing Director of Novocherkassk Electrode Plant
ENERGOPROM Group and SOLVER signed an agreement for construction of the Nipple Center at Novocherkassk Electrode Plant