News El 6 Novosibirsk

EIRICH Mixing Plant Arrives at EPM-NovEP

Novosibirsk, April 10, 2019 EPM-Novosibirsk Electrode Plant (EPM-NovEP, member of EPM) has received the mixing plant EIRICH from Germany.

The cargo with a total weight of 40 tons was delivered from Hartheim (Germany) with eight trailers. The trailers covered the distance of 4.5 thousand km in two weeks. Representatives of EIRICH will also arrive in the near future in order to discuss the upcoming installation of the mixing plant at EPM-NovEP.

The equipment is stored in the warehouse now; after the customs clearance is passed and the required documents are obtained, the experts of EPM-NovEP will move it to the installation site in the paste shop. The work is underway here to prepare for  reception of the equipment for commencement of construction of a new mixing plant.

EIRICH mixing complex will be used to prepare the paste for pressing UHP, SHP, HP, RP brand graphite electrodes.

Construction of the new mixing plant is an investment project of EPM-NovEP aimed at ensuring the uniform quality of the electrodes and improving the reliability of their operation. Capacity of the new complex is five times higher than that of the old type mixers, which will help increase the amount of products. Commissioning of the EIRICH mixing plant is scheduled for Q3 2019.

The contract between EPM Group and EIRICH for installation of the mixing plant was signed in March 2018. Two EIRICH mixing plants are planned to be installed at EPM-NovEP by late 2019. 

EL 6 NOVOSIBIRSK STARTS RAIL CONTAINER DELIVERIES
EL 6 NOVOSIBIRSK PLANTS 150 PYRAMIDAL POPLARS AT EVSINO STATION
EL 6 NOVOSIBIRSK VOLUNTEERS HELD A TRADITIONAL AUTUMN ECO-CAMPAIGN ON THE LOCAL RIVER. ALTHOUGH THEY RETURNED ALMOST EMPTY-HANDED, THEY WERE VERY HAPPY ABOUT IT.
EL 6 NOVOSIBIRSK YOUNG AND SENIOR WORKERS TAKE PART IN CLEAN UP AFTER YOURSELF CAMPAIGN
400 LINYOVO-BASED EMPLOYEES OF EL6 NOVOSIBIRSK TAKE PART IN VOLUNTARY CANCER SURVEY
EL6 TRADITIONALLY PARTNERS THE TAKE A STEP CAREER GUIDANCE GAME
EL 6 Novosibirsk Management System Got ISO Certified
CONSOLIDATION OF ASSETS OF EL 6 (FORMERLY EPM GROUP) HAS BEEN COMPLETED
EPM GROUP AND NSTU SIGN A STRATEGIC PARTNERSHIP AGREEMENT
EPM-NovEP released 1,800 nelma fry into the Ob tributary
EPM-NOVOSIBIRSK ELECTRODE PLANT CONFIRMS COMPLIANCE OF THE MANAGEMENT SYSTEM WITH INTERNATIONAL STANDARDS
EPM-NovEP expands the range of laboratory studies of cathode products
EPM-NovEP receives a new EIRICH mixing plant
EPM-NovEP launches an EIRICH mixing plant to celebrate the 45th anniversary of the production site
EPM-NOVEP INTRODUCED A NEW RING COAL-TAR LINE
EPM-NOVEP LAUNCHED THE ASSEMBLY OF THE GERMAN EIRICH MIXING PLANT
Novosibirsk marked the opening of a traveling photo exhibition dedicated to the 45th anniversary of the EPM – Novosibirsk Electrode Plant
EIRICH Mixing Plant Arrives at EPM-NovEP
Preparatory works for installation of the German mixing plant EIRICH have started at EPM-NovEZ
New Equipment for Production of Electrode Paste Briquettes Put into Operation at EPM-NovEP
Acting Governor of Novosibirsk Region Andrei Travnikov Makes a Working Visit to Novosibirsk Electrode Plant
ENERGOPROM Group and EIRICH GMBH have executed a contract for continuous intensive Mixer for the Novosibirsk Electrode Plant
RUSAL and ENERGOPROM Sign a Long-Term Contract for Supply of Graphite Products