News El 6 Novocherkassk

EPM Group completes project as part of cpecial investment contact

Novocherkassk, December 25, 2019. The advanced four-chamber direct heating Castner graphitization furnace has been brought into operation in the electrode graphitization shop at EPM Novocherkassk Electrode Plant (EPM–NEP, part of the EPM Group).

The construction of the furnace cost RUB 45 million. The new equipment was built in six months at the site, where the indirect heating Acheson furnace was previously operated. The new furnace boasts advanced technical parameters and higher energy efficiency. The Castner furnace reduces the total production cycle time and decreases electricity consumption by more than 35% compared to indirect heating furnaces. In addition, the furnace design and process environment improve the product graphitization quality.

Evgeniy Churikov, Managing Director of  EPM–NEP, commented that the furnace construction was part of the project planned under the Special Investment Contract signed by the Ministry of Industry and Trade of the Russian Federation, the Government of the Rostov Region, and EPM Group. According to the Special Investment Contract, Novocherkassk Electrode Plant will invest more than RUB 2.7 billion in upgrading the graphite electrode production by the end of 2023.

The project also provides for retrofitting Section 1 of the electrode graphitization shop with Castner furnaces (to replace the Acheson furnaces). Within the framework of the project, a total of five furnaces are planned for retrofitting. Another Castner furnace with the similar parameters is currently under construction in the electrode graphitization shop of EPM–NEP.

NUEVOS BENEFICIOS PARA LOS EMPLEADOS DE "EL 6 NOVOCHERKASSK"
MEDICAL CENTER SUPPORTED BY EL 6 NOVOCHERKASSK OPENS IN NOVOCHERKASSK INDUSTRIAL DISTRICT
EL 6 NOVOCHERKASSK PONE EN FUNCIONAMIENTO COMERCIAL EL NUEVO HORNO DE RECOCCIÓN
EL ALMACENAMIENTO Y EL ENVÍO DE PRODUCTOS TERMINADOS EN EL 6 DE NOVOCHERKASSK SERÁN MÁS CONVENIENTES
EL 6 NOVOCHERKASSK INSTALÓ UN NUEVO EQUIPO DE DESEMPOLVADO Y DEPURACIÓN DE GAS EN EL TALLER DE GRAFITIZACIÓN DE ELECTRODOS
DIPUTADOS DE LA DUMA DE LA CIUDAD DE NOVOCHERKASSK VISITARON SUCURSAL EL 6 NOVOCHERKASSK
FINALIZADA LA CONSOLIDACIÓN DE LOS ACTIVOS DEL GRUPO EL 6 (ANTES GRUPO EPM)
SERGUEY YELKOV HA SIDO NOMBRADO DIRECTOR EJECUTIVO DE FÁBRICA DE ELECTRODOS DE NOVOCHERKASK DEL GRUPO EPM
VASILIY OSMAKOV, VICEMINISTRO DE INDUSTRIA Y COMERCIO DE LA FEDERACIÓN DE RUSIA, VISITÓ LA PLANTA DE ELECTRODOS DE EPM EN NOVOCHERKASK
EPM GROUP PUT INTO OPERATION MODERN FOUR-CHAMBER DIRECT HEATING GRAPHITE FURNACE
EPM Group completes project as part of cpecial investment contact
EPM group inaugurated the new RIEDHAMMER furnace at EPM-NEZ
Construction of a modern RIEDHAMMER furnace complete at EPM – NEP
A robot-assisted nipple manufacturing centre has been officially commisioned at EPM-NEP
Equipment Delivered to EPM-NEP Nipple Centre
EPM-NEP will have new high-precision measuring equipment for graphite electrode nipples
Novocherkassk Electrode Plant Started Preparatory Works for New RIEDHAMMER Furnace
ENERGOPROM has commissioned a new pitch impregnation line at Novocherkassk Electrode Plant
Novocherkassk Electrode Plant launches modernized baking furnace
Evgeniy Churikov Appointed Managing Director of Novocherkassk Electrode Plant
ENERGOPROM Group and SOLVER signed an agreement for construction of the Nipple Center at Novocherkassk Electrode Plant